Utilities Bury More Transmission Lines to Prevent Storm Damage

Facing hurricanes and public opposition to overhead lines, utilities are paying extra to go underground.


Buried Power: A crew from New River Electrical buries 800 meters of transmission cables at a substation in Connecticut.  (Photo Credit:  New River Electrical) Click to Enlarge.
In the past six months, transmission lines have been destroyed by hurricanes in Puerto Rico, singed by wildfires in California, and bitterly opposed by residents in Utah and Pennsylvania who want to stop utilities from building more.

Such problems have grid operators literally thinking deeper.  Increasingly, utilities in the United States and elsewhere are routing power underground.  Puerto Rico’s grid rebuild is a prime example:  A proposal, crafted by an industry-government consortium late last year, calls for “undergrounding” transmission to harden a power system still recovering from Hurricanes Irma and Maria.

Much of the plan’s outlay for transmission—US $4.3 billion—would create hardy overhead circuits interspersed with underground cables in areas where gusts could snap even the strongest lines and towers.  A $601 million line item also provides for a buried high-voltage direct current (HVDC) cable around the territory’s southeast corner, where most big storms strike first.  This underground bypass would create a secure path from the island’s most efficient power plants to the heavily populated area around San Juan.

By heading below ground, transmission grids are following a path laid by their lower-voltage cousins—distribution grids.  In some cities, power distribution occurs entirely out of sight.  This is possible thanks to specialized cables, whose metal conductors are wrapped in cross-linked polyethylene, a heat—stable insulator, as well as metal and polymer layers providing electrical shielding, impermeability to water, and puncture resistance.

Utilities have been slower to bury transmission because of the expense, according to power consultant Ken Hall, a former transmission and distribution director at the Edison Electric Institute, a Washington, D.C.–based utility trade group.  Transmission lines operate at higher power levels than distribution lines and generate more heat, which is harder to dissipate underground.

Doing it properly can mean burying up to a dozen cables at a time to carry the current, and specifying thick copper conductors that have lower resistance and generate less heat than the cheaper aluminum employed in overhead lines.  Each cable must be shipped in roughly 1-kilometer-long links and stitched together on-site, adding further to the tab.

Tally it all up, says Hall, and underground transmission costs roughly 5 to 10 times as much per kilometer as overhead circuits.  “Every utility in the United States has underground distribution.  But not every utility has underground transmission,” he notes.
...
In the United States utilities have promised to bury lines along nearly one-third of the ­long-disputed 309-kilometer Northern Pass ­project—a set of AC and HVDC links meant to deliver more Canadian hydropower to the northeastern United States.  The intent was to eliminate the “visual impacts” of tall towers and suspended lines on New Hampshire’s White Mountains, which are popular with tourists.  State regulators will vote on the project in February.

Read more at Utilities Bury More Transmission Lines to Prevent Storm Damage